Items allocated across projects/tasks


This exception is displayed by the planning workbench.

It simply means that supply for one project has been allocated to the demand of a different project.

To resolve this issue, check the demand. If the demand is correct, you should:
  • Perform project transfers if exception message is related to on hand quantities
  • Update purchase and work orders if exception message is not related to on-hand quantities.
We will assume that you are using a Project tracking environment and that the following planning parameters are set up as follow:
  • Planning reservation option is set to Planning Group.
  • All projects belong to the same planning group.
  • Pegging is set to Hard Pegging.
Check the meaning of other exceptions from the planning engine here: MRP most frequently used exceptions